Обязанности и достижения:
LLC "SFERA", Investment-Construction company, Tula, Head of works on the project (PM);
Objects: Priority investment projects of the Customer - JSC "IES-Holding": Vladimir TEZ-2 (Vladimir),
Novogorkovskaya TEZ (Kstovo of the Nizhny Novgorod region.), Academic TEZ (Ekaterinburg)
Responsibilities: Organization and control for the execution of contracts with Vendors, Contractors and
Client of the Installation, PCC and commissioning activities of Gas booster compressor plant and other industrial
equipment for power engineering objects.
Control of the installation and commissioning of the next systems: power supply 0,4/6 kV,
Instrumentation, Internal gas pipelines, Gas cooling system, Purification and Compression of natural gas system,
HVAC, FAS, PAS, Fire extinguishing systems, oil supply, Nitrogen and Compressed Air generation systems,
Control systems of technological processes and integration it into the automatic control system of technological
processes of the power plant. Monitoring for the preparation and issue of base primary documentation, permissive,
and executive documentation. Monitoring for the manufacturing equipment processes, executing the factory test,
shipment, delivery, unloading on the site. Organization of Chief-supervision for installation and commissioning
activities. Participation in local booster gas compressors tests and complete Plant testing, elimination of the punch
items, Handover station to the Client.
Managing and supervision of contractors and sub-contractors (LLC "Tsentrenergoservis", LLC
"Uralenergomontazh", LLC "LOT"), Chief engineers of the Borsig ZM Compression company (equipment
supplier) and its subcontractors and sub vendors (Avicomp, BBM Akustik, Minimax, Eusebi Impianti and other).
Performing technical meetings with Client and Contractor. Reporting to Management and the Client of work
progress. Development and updating schedules.
In submission: 2 engineers
Achievements: Fankfull review from the Customer - JSC "IES - holding" with the subsequent bonus
payments. Participation in the commissioning of 3 booster gas compressor stations with the point of gas
preparat.